Oceanic Exploration
Feasibility Study for the East Timor Pipeline



2.3 RECOMMENDIATIONS
  • More detailed information is required of the pipeline route, geotechnical nature of the route and environmental data.
  • Further engineering needs to be performed to determine accurately the pipeline dimensions and wall thicknesses.
  • The LNG location at Suai needs to be considered further, including the ease of docking LNG tankers there.
  • Consider alternative landfall locations, which may provide easier access to the domestic market.

W:\Oil&Gas\Joint Ventures\Intec\Projects\Pw Perth projects\0063.01 Oceanic East Timor\P0063.01Rev 1-with changes.doc
Page 3        13 June 2002