COST BREAKDOWN FOR 28" OUTSIDE DIAMETER OPTION 3
Pipeline Diameter 28 inches
Wall Thickness single mm
Coating Thickness FBE
Installation Method Lay Barge J Lay
Line Length 220 Km From Greater Sunrise to Bayu Undan
COST ITEM RATE US$   AMOUNT   COST US$ AREA TOTAL
            US$
1.0 Materials & Transportation      
       
1.1 Pipe/Corrosion Coating 1355 Tonne 71,280 tonne 96,584,400  
1.2 Concrete Coating 150 Tonne 80,210 tonne 12,031,500  
1.3 Material transport 1.00 $/m 220,000 m 220,000  
1.4 Spoolpieces 100,000 $ each 2 off 200,000  
1.5 Anodes 450 $ each 1,833 off 824,850  
1.6 Riser 200,000 $ each 2   400,000  
       
      $110,260,750
             
             
2.0 Shore Approach      
       
2.1 Land fall 28,000,000 $ 0   0  
2.2 Trenching/Stabilisation 12,000,000 $ each 0   0  
      $0
       
3.0 Route Survey            
       
3.1 pre survey vessel 12,000 $/day 70.0 days 840,000  
      $840,000
             
4.0 Offshore Installation            
       
4.1 DSV 100,000 $/day 30.00 days 3,000,000  
4.2 laybarge 300,000 $/day 55.0 days 16,500,000  
       
       
       
      $19,500,000
             
5.0 Mobilisation / Demobilisation      
       
5.1 Pre survey vessel 150,000 $ 1   150,000  
5.2 DSV 750,000 $ 1   750,000  
5.3 Laybarge 10,000,000 $ 1   10,000,000  
       
       
      $10,900,000
             
    SUB TOTAL - DIRECT COSTS $141,500,750
             
6.0 Indirect Costs      
       
6.1 Engineering & Project Mangt.(1.0-5.0) 4.0% 141,500,750   5,660,030  
6.2 Procurement (1.2 - 1.6) 10.0% 13,676,350   1,367,635  
6.3 Inspection (1.2 - 1.6) 6.0% 1,644,850   98,691  
6.4 Supervision (2.0-4.0) 4.0% 20,340,000   813,600  
6.5 Insurance (2.0-5.0) 4.0% 141,500,750   5,660,030  
      $13,599,986
             
7.0 Contingencies      
       
7.1 Materials (1.0) 10.0% 110,260,750   11,026,075  
7.2 Shore Approach (2.0) 15.0% 0   0  
7.3 Route Survey (3.0) 10.0% 840,000   84,000  
7.3 Offshore (4.0) 12.5% 19,500,000   2,437,500  
7.4 Mobilisation / Demobilisation (5.0) 10.0% 10,900,000   1,090,000  
7.5 Indirect Costs (6.0) 10.0% 13,599,986   1,359,999  
      $15,997,574
             
  SUB TOTAL - INDIRECT COSTS $29,597,560
             
  TOTAL FOR PIPELINE  
            $171,098,310