COST BREAKDOWN FOR 10" OUTSIDE DIAMETER OPTION 2
Pipeline Diameter 10 inches
Wall Thickness multiple mm
Coating Thickness FBE
Installation Method Lay Barge J Lay
Line Length 230 Km From Bayu to Suai
COST ITEM RATE US$   AMOUNT   COST US$ AREA TOTAL
            US$
1.0 Materials & Transportation      
       
1.1 Heavy Wall Pipe/Corrosion Coating 1355 Tonne 8,792 tonne 11,913,160  
1.2 Standard Wall Pipe/Corrosion Coating 1355 Tonne 13,324 tonne 18,054,020  
1.3 Material transport 1.00 $/m 230,000 m 230,000  
1.4 Spoolpieces 75,000 $ each 1 off 75,000  
1.5 Anodes 300 $ each 1,916 off 574,800  
1.6 Riser 150,000 $ each 1   150,000  
      $30,996,980
             
             
2.0 Shore Approach      
       
2.1 Land fall 25,000,000 $ 1   25,000,000  
2.2 Trenching/Stabilisation 8,000,000 $ each 1   8,000,000  
      $33,000,000
       
3.0 Route Survey            
       
3.1 pre survey vessel 12,000 $/day 90.0 days 1,080,000  
      $1,080,000
             
4.0 Offshore Installation            
       
4.1 DSV 100,000 $/day 30.00 days 3,000,000  
4.2 laybarge 550,000 $/day 58.0 days 31,900,000  
       
       
       
      $34,900,000
             
5.0 Mobilisation / Demobilisation      
       
5.1 Pre survey vessel 150,000 $ 1   150,000  
5.2 DSV 750,000 $ 1   750,000  
5.3 Laybarge 12,500,000 $ 1   12,500,000  
       
       
      $13,400,000
             
    SUB TOTAL - DIRECT COSTS $113,376,980
             
6.0 Indirect Costs      
       
6.1 Engineering & Project Mangt.(1.0-5.0) 4.0% 113,376,980   4,535,079  
6.2 Procurement (1.2 - 1.6) 10.0% 19,083,820   1,908,382  
6.3 Inspection (1.2 - 1.6) 6.0% 19,083,820   1,145,029  
6.4 Supervision (2.0-4.0) 4.0% 68,980,000   2,759,200  
6.5 Insurance (2.0-5.0) 4.0% 113,376,980   4,535,079  
      $14,882,770
             
7.0 Contingencies      
       
7.1 Materials (1.0) 10.0% 30,996,980   3,099,698  
7.2 Shore Approach (2.0) 15.0% 33,000,000   4,950,000  
7.3 Route Survey (3.0) 10.0% 1,080,000   108,000  
7.3 Offshore (4.0) 12.5% 34,900,000   4,362,500  
7.4 Mobilisation / Demobilisation (5.0) 10.0% 13,400,000   1,340,000  
7.5 Indirect Costs (6.0) 10.0% 14,882,770   1,488,277  
      $15,348,475
             
  SUB TOTAL - INDIRECT COSTS $30,231,245
             
  TOTAL FOR PIPELINE  
            $143,608,225