COST BREAKDOWN FOR 28" OUTSIDE DIAMETER OPTION 1
Pipeline Diameter 28 inches
Wall Thickness multiple mm
Coating Thickness FBE
Installation Method Lay Barge J Lay
Line Length 230 Km From Bayu to Suai
COST ITEM RATE US$   AMOUNT   COST US$ AREA TOTAL
            US$
1.0 Materials & Transportation      
       
1.1 Heavy Wall Pipe/Corrosion Coating 1355 Tonne 40,733 tonne 55,193,215  
1.2 Standard Wall Pipe/Corrosion Coating 1355 Tonne 81,351 tonne 110,230,605  
1.3 Material transport 1.00 $/m 230,000 m 230,000  
1.4 Spoolpieces 100,000 $ each 1 off 100,000  
1.5 Anodes 450 $ each 1,916 off 862,200  
1.6 Riser 200,000 $ each 1   200,000  
      $166,816,020
             
             
2.0 Shore Approach      
       
2.1 Land fall 28,000,000 $ 1   28,000,000  
2.2 Trenching/Stabilisation 12,000,000 $ each 1   12,000,000  
      $40,000,000
       
3.0 Route Survey            
       
3.1 pre survey vessel 12,000 $/day 90.0 days 1,080,000  
      $1,080,000
             
4.0 Offshore Installation            
       
4.1 DSV 100,000 $/day 30.00 days 3,000,000  
4.2 laybarge 550,000 $/day 77.0 days 42,350,000  
       
       
       
      $45,350,000
             
5.0 Mobilisation / Demobilisation      
       
5.1 Pre survey vessel 150,000 $ 1   150,000  
5.2 DSV 750,000 $ 1   750,000  
5.3 Laybarge 12,500,000 $ 1   12,500,000  
       
       
      $13,400,000
             
    SUB TOTAL - DIRECT COSTS $266,646,020
             
6.0 Indirect Costs      
       
6.1 Engineering & Project Mangt.(1.0-5.0) 4.0% 266,646,020   10,665,841  
6.2 Procurement (1.3 - 1.6) 10.0% 1,392,200   139,220  
6.3 Inspection (1.3 - 1.6) 6.0% 1,392,200   83,532  
6.4 Supervision (2.0-4.0) 4.0% 86,430,000   3,457,200  
6.5 Insurance (2.0-5.0) 4.0% 99,830,000   3,993,200  
      $18,338,993
             
7.0 Contingencies      
       
7.1 Materials (1.0) 10.0% 166,816,020   16,681,602  
7.2 Shore Approach (2.0) 15.0% 40,000,000   6,000,000  
7.3 Route Survey (3.0) 10.0% 1,080,000   108,000  
7.3 Offshore (4.0) 12.5% 45,350,000   5,668,750  
7.4 Mobilisation / Demobilisation (5.0) 10.0% 13,400,000   1,340,000  
7.5 Indirect Costs (6.0) 10.0% 18,338,993   1,833,899  
      $31,632,251
             
  SUB TOTAL - INDIRECT COSTS $49,971,244
             
  TOTAL FOR PIPELINE  
            $316,617,264